September Development Update
September 2026 construction archive documenting the completion of Swiss Park playground equipment, tiered amphitheater seating, 1st Roundabout horticulture, Indoor Arena slab reinforcement, and deep underground sewerage lines.
Swiss Park & 1st Roundabout: Multi-slide children's play area installed on manicured lawns alongside the central roundabout.
Amphitheater & Sportsplex: Tiered concrete seating bowl and fenced multi-sport courts taking shape.
Indoor Arena & Swiss Town Houses: Roof slab steel reinforcement bar fixing and multi-storey brick masonry.
Underground Sewerage Network: Deep trench excavation, RCC pipe lowering, and manhole construction across Swiss Executive.
September 2026 Progress Gallery
Swiss Park children's play area installation, open-air amphitheater tiered concrete seating, 1st Roundabout landscaping, Indoor Arena roof slab steel fixing, Swiss Executive trunk sewerage laying, and road compaction works.