The published project delivery schedule sets out milestone windows for Swiss Executive, Swiss East, Swiss Central, Swiss Capital, and Swiss West.

Royal Swiss Housing Multan project delivery schedule
Royal Swiss Housing Multan project delivery scheduleOpen full resolution

Sector delivery windows

SectorDevelopmentAsphaltPossessionBoundary wall
Swiss ExecutiveIn progressMay 2026August 2026August 2026
Swiss EastIn progressAugust 2026November 2026August 2026
Swiss CentralIn progressFebruary 2027May 2027May 2027
Swiss CapitalMay 2026June 2027September 2027September 2027
Swiss WestJuly 2026September 2027December 2027December 2027